SKOURIES (GREECE)
This copper-gold mine uses a combination of conventional open pit and underground mining techniques. Based on the 2022 Project Feasibility Study, the initial life of mine is 20 years, and it is expected to produce on average 140,000 ounces of gold and 67 million pounds of copper per year. First copper-gold concentrate was produced on September 8, 2026, with commercial production expected in the fourth quarter of 2026.
Skouries Progress
Updated: July 2026
Advancing Skouries
First production of copper-gold concentrate was achieved on September 8, 2026, with commercial production expected in the fourth quarter of 2026.
The Company has secured concentrate agreements with multiple offtakers for all anticipated Skouries production volumes for the next two years, with additional counterparty agreements in process covering production through to 2029. Market conditions for copper-gold concentrate remain highly competitive.
With commercial production expected in late Q4, total project capital for Skouries is estimated at approximately $1.425 billion, an increase that consists of $65 million of projects costs and $45 million of previously guided growth capital that had been expected following commercial production but is now expected to be incurred prior to commercial production and is therefore reported as project capital. The increase primarily reflects higher contractor requirements to complete construction and commissioning activities, the extended use of temporary generator sets prior to connection to permanent grid power, additional owner's costs and other project execution-related costs associated with the longer commissioning period.
Accelerated operational capital is expected to total $390 million, an increase that consists of $95 million of additional operational costs and $35 million of previously guided sustaining capital that had been expected following commercial production. It is now expected to be incurred and capitalized during the pre-commercial production period and is therefore reported as accelerated operating capital. This increase is separate from the increase in project capital.
Up to an additional $30 million may be incurred, depending on the exact timing of commercial production. The classification of these expenditures will depend on when commercial production is achieved, with amounts potentially reflected in project capital, AOC, sustaining capital or growth capital.
Based on the Company's current schedule and cost assumptions, the project remains fully funded through available cash, operating cash flow and existing debt facilities.
The Term Facility totally €740.4 million ($840.7million) is fully drawn (including the Contingent Overrun Facility of €60.0 million which was drawn in Q2 2026).(1)
Project capital totalled $108.6 million in Q3 2026 and $398.9 million during the nine months ended September 30, 2026. Accelerated operational capital cost totalled $84.3 million in Q3 2026, and $192.5 million during the nine months ended September 30, 2026. At September 30, 2026, cumulative project capital invested towards Phase 2 of construction totalled $1.379 billion, and the cumulative accelerated operational capital totalled $285.6 million.
Primary Crusher Building
The primary crusher crushed first ore in July and is now operating as part of the integrated processing circuit. The stockpile dome, ancillary feeders and associated chute work are complete and supporting ongoing operations.
Process Plant
The process plant is substantially complete, and operating as part of the ongoing ramp-up of the operation. Commissioning activities have advanced across the processing circuit, with ore being processes through to concentrate production. Optimization and performance testing of various systems continue as part of the ramp-up to commercial production.
Thickeners
Two of the three tailings thickeners have been commissioned and are supporting current operations. Construction of the third tailings thickener, which is not required to achieve commercial production, is progressing, with completion expected in Q4 2026.
Filtered Tailings Facility
Commissioning of the filtered tailings facility continues to progress with two of the six filter presses operational. With these filter presses online, the plant is operating continuously and progressively increasing throughout as commissioning advances and the remaining filter presses are brought online. Commissioning of the remaining four filter presses is expected to be completed in November 2026.
Associated tailings handling infrastructure continues to be commissioned to support long-term operations.
Powerline and Substations
The site was successfully energized on September 28, 2026, marking the completion of its connection to permanent grid power. The connection supports the ongoing commissioning and ramp-up of key systems across the site and provides the reliable, long-term power infrastructure required for the operations. All the temporary generators have been demobilized and removed from site.
Integrated Extractive Waste Management Facility
The initial filtered tailings placement areas are well advanced. The platform for the tailings stacker is complete and ready for assembly, while the access ramp and platform for the mobile (grasshopper) conveyors have been excavated and prepared for placement of the conveyor units. Construction of the rock buttress supporting the downstream embankment of the first filtered tailings placement area in the Karatza Lakkos ("KL") valley is progressing and will be completed ahead of tailings placement. Foundation preparation for the first phase of the KL filtered tailings embankment is substantially complete, and placement of engineered fill is underway across the full footprint. Construction of the low-grade ore stockpile continued advancing. The lower section has been completed and construction is now focusing on the upper section.
Open Pit Mining
The open pit mine is feeding the crusher from both the stockpile and directly from the open pit. At the end of Q3 2026, the stockpiles contained approximately 4.8 million tonnes of open pit and underground ore, representing an estimated 176,000 ounces of gold and 61 million pounds of copper.
Underground Development
The underground mine delivered 179 kt of ore to stockpiles during Q3 2026. Underground development continued according to plan, with a total of 2,101 metres of development during the quarter. The east ramp breakthrough to the underground works was achieved during the quarter and both ramps are now providing access in and out of the underground.
Workforce
As at September 30, 2026, there were approximately 2,297 personnel working on site, including 622 Skouries employees.
(1) See the section "Financial Condition and Liquidity - Financing Activities" in the Company's September 30, 2026 MD&A.
KEY HIGHLIGHTS
Location
Mine type
Metals mined
Initial expected mine life
Deposit type
Ownership
*Based on Proven & Probable Mineral Reserves. Refer to Reserves and Resources for more information on Mineral Reserves.
Virtual Tour
Sustainable Environmental Design
Filtered Tailings
The Skouries project design includes filtered tailings, an innovative method that makes the tailings management process safer and provides additional environmental benefits compared to other tailings management options. During mining, ore is crushed, ground and processed to separate valuable minerals from the surrounding rock. The residual leftover rock and water from this process is called tailings. Traditionally, tailings were stored in liquid form in large facilities, known as tailings ponds. Modern filtered methods remove the excess water resulting in a sandy material which is then stacked and compressed. Less space is required for its storage into tailings management facility areas (TMF).
At Skouries, only one TMF will be required, instead of the two that were planned in the initial design and would have been required in the case of traditional liquid tailings management.
Eldorado has used this technology successfully at our Efemçukuru operation in Türkiye and at our Olympias Mine in Greece. Filtered tailings offer major environmental benefits such as:
Geotechnical stability
Up to 90% of the water is removed from the tailings using filtration. These de-watered solids (similar to a moist sand) are then conveyed and compacted within the storage facility to form a geotechnically stable & solid mass.
Water savings
Filtered tailings technology enables us to maximize water recycling and re-use it in the production cycle, thereby minimizing the consumption of fresh water.
Smaller footprint
Filtered tailings result in up to a 40% smaller environmental footprint, further minimizing environmental impact.
Protection of Water and Facilities
We are reducing water consumption with targeted projects, such as filtering and recycling. We are also reducing groundwater inflows by pre-draining waters and re-injecting them into the aquifer. For water outside the mine site, we have constructed water diversion channels to keep surface waters from even entering the mine site. For water that unavoidably comes into contact with mining activities at the mine, we will both have a water treatment plant and re-use water in day-to-day operations.
Parallel Rehabilitation
The rehabilitation of liquid tailings disposal sites is usually possible after the end of a mine’s lifetime. Thanks to the filtered method, due to the solid form of the tailings, it is possible to gradually regenerate the disposal facilities in parallel with mining activities. That means that the site will be rehabilitated and ready to hand back to the local community sooner after the end of mining activity.
Backfilling tunnels & open pit with mining tailings
Part of the pre-strip material from the open pit is used to build the waste rock dam, water management-ponds and various other site infrastructure works. The excess will be used to gradually rehabilitate the tailings management facility. Mining tailings will be used to fill in the areas that were mined out in the underground mine, as well as the open pit to restore the original terrain.
90%
Water removed from tailings
40%
Smaller environmental footprint with dry-stack technology
Indicative Operating Data
The initial mine life is 20 years, based on Skouries Technical Report (NI 43-101) published January, 2022
| Total Mineralized Material Mined | 147 Mt |
| Average annual gold production | 140,000 oz |
| Average annual copper production | 67 Mlbs |
| Average cash operating costs (LOM) | $(365)/oz |
| Average AISC (LOM) | $(6)/oz sold |
| Gold recovery | 83% |
| Copper recovery | 90% |
| Au grade | 0.77 g/t Au |
| Cu grade | 0.50% Cu |
| Initial Capital Costs (US $) - Initial Phase 1 Capex | $845 M |
| Total sustaining capex (US $) | $850 M |
| Gold price | $1,500/oz |
| Copper price assumption used in financial analysis | $3.85/lb |
| (US $) | $1.3 B |
| IRR (after tax) | 19% |
| Payback period | < 4 years |
Geology and Mineralization
The Skouries porphyry copper-gold deposit is centred on a small (less than 400m in diameter), pencil-porphyry stock that intruded schist and gneiss of the Paleozoic Vertiskos Formation of the Serbo-Macedonian Massif, NE Greece. Mineralization extends for more than 920m depth from surface.
The porphyry is characterized by at least four intrusive phases that are of probable monzonite to syenite composition, but contain an intense potassic alteration and related stockwork veining that overprints the original protolith.
Potassic alteration and copper mineralization also extend into the country rock; approximately two thirds of the measured and indicated tonnes and 40% of the contained metal are hosted outside the porphyry.
The potassic alteration is syn- to late-magmatic in timing and is characterized by K-feldspar overgrowths on plagioclase, secondary biotite replacement of igneous hornblende and biotite, and a fine-grained groundmass of K-feldspar-quartz with disseminated magnetite.
Four main stages of veining are recognized: 1) an early stage of intense quartz-magnetite stockwork; 2) quartz-magnetite veinlets with chalcopyrite ± bornite; 3) quartz-biotite-chalcopyrite ± bornite-apatite-magnetite veinlets; and 4) a localized, late stage set of pyrite ± chalcopyrite-calcite-quartz veins. The host porphyry and potassic alteration at Skouries were coeval and formed during the Early Miocene.
EXPLORATION
Exploration at Skouries is focused on identifying and testing porphyry targets within the project area, including the Tsikara and Fisoka prospects. Ongoing targeting activities include geological mapping, systematic soil sampling and geophysical surveying.
Skouries Project Brochure
REPORTS
| REPORT TITLE | LINK |
|---|---|
| Skouries Technical Report - January 2022 | Download PDF |
| Skouries Technical Report - March 2018 | Download PDF |
| Skouries Technical Report - July 2011 | Download PDF |
Environmental and Social Impact Assessment (ESIA)
| REPORT TITLE | LINK |
|---|---|
| Non-technical summary (NTS) | Download PDF |
| Complete assessment file (ZIP) | View Reports |
| ESIA appendices | View Reports |
| ESMS framework | Download PDF |
| Stakeholder Engagement Plan | Download PDF |
| E&A Management Plans | View Reports |
| Environmental & Social Action Plan | Download PDF |
Regulatory Environmental Impact Assessment (EIA)
| REPORT TITLE | LINK |
|---|---|
| Non-technical summary (NTS) | Download PDF |
| Complete assessment file | View Reports |
| EIA appendices | Download PDF |
| EIA maps / drawings | View Reports |