The Skouries project is a world-class asset located on the Halkidiki Peninsula in northern Greece.

This high-grade copper-gold porphyry deposit will be mined using a combination of conventional open pit and underground mining techniques. The initial life of mine is 20 years, and it is expected to produce on average 140,000 ounces of gold and 67 million pounds of copper per year. First production is expected in the third quarter of 2025, with commercial production at the end of 2025.

Skouries Project Progress

Updated: Q3 2024

Advancing Skouries

By the end of the third quarter of 2024, overall project progress was 79% complete including the first phase of construction. First production is expected in the third quarter of 2025, with commercial production at the end of 2025.

KEY HIGHLIGHTS

Location

Halkidiki Peninsula, Greece

Mine type

Open pit and underground

Metals mined

Copper, Gold

Initial expected mine life

20 years*

Deposit type

Copper-gold porphyry

Ownership

100%

*Based on Proven & Probable Mineral Reserves. Refer to Reserves and Resources for more information on Mineral Reserves.

Virtual Tour

Best-in-class Environmental Design

Dry-stack Tailings

The Skouries project design includes dry-stack tailings, an innovative method that makes the tailings management process safer and provides additional environmental benefits compared to other tailings management options. During mining, ore is crushed, ground and processed to separate valuable minerals from the surrounding rock. The residual leftover rock and water from this process is called tailings. Traditionally, tailings were stored in liquid form in large facilities, known as tailings ponds. Modern dry stacking methods remove the excess water resulting in a sandy material which is then stacked and compressed. Less space is required for its storage into tailings management facility areas (TMF).

At Skouries, only one TMF will be required, instead of the two that were planned in the initial design and would have been required in the case of traditional liquid tailings management.

Eldorado has used this technology successfully at our Efemçukuru operation in Türkiye and at our Olympias Mine in Greece. Dry stacking offers major environmental benefits such as:

Geotechnical stability

Up to 90% of the water is removed from the tailings using filtration. These de-watered solids (similar to a moist sand) are then conveyed and compacted within the storage facility to form a geotechnically stable & solid mass.

Water savings

Dry stacking technology enables us to maximize water recycling and re-use it in the production cycle, thereby minimizing the consumption of fresh water.

Smaller footprint

Dry-stack tailings result in up to a 40% smaller environmental footprint, further minimizing environmental impact.

Protection of Water and Facilities

We are reducing water consumption with targeted projects, such as filtering and recycling. We are also reducing groundwater inflows by pre-draining waters and re-injecting them into the aquifer. For water outside the mine site, we have constructed water diversion channels to keep surface waters from even entering the mine site. For water that unavoidably comes into contact with mining activities at the mine, we will both have a water treatment plant and re-use water in day-to-day operations.

Parallel Rehabilitation

The rehabilitation of liquid tailings disposal sites is usually possible after the end of a mine’s lifetime. Thanks to the dry stacking method, due to the solid form of the tailings, it is possible to gradually regenerate the disposal facilities in parallel with mining activities. That means that the site will be rehabilitated and ready to hand back to the local community sooner after the end of mining activity.

Backfilling tunnels & open pit with mining tailings

Part of the pre-strip material from the open pit is used to build the waste rock dam, water management-ponds and various other site infrastructure works. The excess will be used to gradually rehabilitate the tailings management facility. Mining tailings will be used to fill in the areas that were mined out in the underground mine, as well as the open pit to restore the original terrain.

90%

Water removed from tailings

40%

Smaller environmental footprint with dry-stack technology

Indicative Operating Data

The initial mine life is 20 years, based on Skouries Technical Report (NI 43-101) published January, 2022

Total Mineralized Material Mined147 Mt
Average annual gold production 140,000 oz
Average annual copper production67 Mlbs
Average cash operating costs (LOM) $(365)/oz
Average AISC (LOM) $(6)/oz sold
Gold recovery 83%
Copper recovery 90%
Au grade0.77 g/t Au
Cu grade0.50% Cu
Initial Capital Costs (US $) - Initial Phase 1 Capex$845 M
Total sustaining capex (US $)$850 M
Gold price$1,500/oz
Copper price assumption used in financial analysis$3.85/lb
(US $)$1.3 B
IRR (after tax)19%
Payback period< 4 years
Skouries Project Brochure

Skouries Project Brochure

Skouries is a world-class project designed on the principles of responsible mining; integrating the best environmental and social practices in our industry. Learn more in our project brochure.

REPORTS

REPORT TITLE LINK
Skouries Technical Report - January 2022 Download PDF
Skouries Technical Report - March 2018 Download PDF
Skouries Technical Report - July 2011 Download PDF

Environmental and Social Impact Assessment (ESIA)

REPORT TITLE LINK
Non-technical summary (NTS) Download PDF
Complete assessment file (ZIP) View Reports
ESIA appendices View Reports
ESMS framework Download PDF
Stakeholder Engagement Plan Download PDF
E&A Management Plans View Reports
Environmental & Social Action Plan Download PDF

Regulatory Environmental Impact Assessment (EIA)

REPORT TITLE LINK
Non-technical summary (NTS) Download PDF
Complete assessment file View Reports
EIA appendices Download PDF
EIA maps / drawings View Reports

Skouries Overview Video

Updated: December 2022

Our Stories

Two heavy haul trucks driving up a road at sunset
Dec 04, 2024

Safety technology explained: Collision avoidance

Eldorado's Executive Vice President of Technical Services and Operations, Simon Hille, presents a cheque for $55,670 to Covenant House Vancouver staff.
Dec 03, 2024

Over $55,000 raised in support of youth experiencing homelessness

women in mine
Nov 05, 2024

Tele-remote tech boosts safety and productivity