Eldorado Announces Preliminary 2015 Operational Results and 2016 Guidance
TSX: ELD
Highlights
- Gold production of 723,532 ounces (including production from tailings retreatment at Olympias), exceeding 2015 guidance of 640,000-700,000 ounces of gold.
- 2015 all-in sustaining cash costs averaged
$841 per ounce; cash operating costs averaged$552 per ounce; lower than original 2015 guidance of$570-615 per ounce. - Closed the year with total liquidity of approximately
$665 million , including$290 million in cash, cash equivalents and term deposits, and$375 million in undrawn lines of credit. - 2016 forecast gold production estimated to be 565,000-630,000ounces of gold at an average cash cost ranging between
$585-620 per ounce, and an all-in sustaining cash cost between$940-980 per ounce.
"I am very pleased to report another strong year of production. For the third year in a row, all of our operating mines met or exceeded original production and cost guidance. Our teams continue to operate safely and to the highest of international safety standards, as evidenced by a 30% improvement in accident rates across our global operations. We are continuing to partner with all of our local communities and invest in their long-term growth." stated
"Looking at Eldorado's long-term plan, the Company remains committed to its portfolio of Greek assets and the realizable benefits to all of the stakeholders involved. Our operations in
Eldorado's year-end financial statements are scheduled to be released on
The Company is also conducting its annual impairment review and preliminary analysis indicates an impairment expense of approximately of
Throughout this press release we use cash operating cost per ounce, and all-in sustaining cost per ounce as additional measures of Company performance. These are non IFRS measures. Please see page our Third Quarter 2015 MD&A for an explanation and discussion of these non IFRS measures. All dollar amounts are stated in US dollars unless stated otherwise. |
2015 Operating Results
Q4 2015 |
YTD 2015 |
|||
Total |
||||
Realized gold price ($/oz) |
1,105 |
1,168 |
||
Gold sold (oz) |
171,310 |
705,310 |
||
Gold produced (oz) 1 |
169,732 |
723,532 |
||
Cash cost ($/oz) |
567 |
552 |
||
|
||||
Gold sold (oz) |
64,395 |
280,892 |
||
Gold produced (oz) |
64,574 |
281,280 |
||
Tonnes to pad |
4,755,500 |
19,146,685 |
||
Grade (g/t) |
0.68 |
0.70 |
||
Cash cost ($/oz) |
510 |
543 |
||
|
||||
Gold sold (oz) |
25,897 |
99,147 |
||
Gold produced (oz) |
24,434 |
100,482 |
||
Tonnes milled |
118,870 |
454,863 |
||
Grade (g/t) |
7.21 |
7.82 |
||
Cash cost ($/oz) |
559 |
521 |
||
|
||||
Gold sold (oz) |
41,979 |
149,552 |
||
Gold produced (oz) |
36,707 |
149,655 |
||
Tonnes milled |
313,119 |
1,303,863 |
||
Grade (g/t) |
4.13 |
4.13 |
||
Cash cost ($/oz) |
641 |
587 |
||
|
||||
Gold sold (oz) |
16,808 |
97,563 |
||
Gold produced (oz) |
16,808 |
97,563 |
||
Tonnes milled |
256,371 |
1,060,176 |
||
Grade (g/t) |
2.41 |
3.14 |
||
Cash cost ($/oz) |
656 |
473 |
||
|
||||
Gold sold (oz) |
22,231 |
78,156 |
||
Gold produced (oz) |
22,231 |
78,156 |
||
Tonnes milled |
217,950 |
849,335 |
||
Grade (g/t) |
3.83 |
3.30 |
||
Cash cost ($/oz) |
536 |
652 |
||
|
||||
Gold sold (oz) |
- |
- |
||
Gold produced (oz) 2 |
4,978 |
16,396 |
||
Tailings re-processed (t) |
166,427 |
589,675 |
||
Grade (g/t) |
2.25 |
1.99 |
||
Cash cost ($/oz) |
- |
- |
||
|
||||
Tonnes sold (t) |
14,007 |
46,502 |
||
Tonnes produced (t) |
11,734 |
40,232 |
||
Cash cost ($/t) |
713 |
774 |
||
|
||||
Tonnes sold (t) |
- |
47,815 |
||
Tonnes produced (t) |
- |
16,038 |
||
Cash cost ($/t) |
- |
33 |
||
1 Includes Olympias tailings retreatment |
||
2 All tailings retreatment |
||
2016 Guidance
Mine |
Production |
Cash Costs |
Sustaining Capital |
|||
Kisladag |
225,000-240,000 |
550-600 |
50 |
|||
Efemcukuru |
90,000-100,000 |
550-600 |
20 |
|||
Jinfeng |
95,000-105,000 |
700-750 |
15 |
|||
Tanjianshan |
70,000-80,000 |
675-725 |
5 |
|||
|
75,000-85,000 |
625-675 |
15 |
|||
Eastern Dragon |
10,000-20,000 |
125-175 |
0 |
|||
Total |
565,000-630,000 |
585-620 |
105 |
|||
2016 Capital Expenditure
($M) |
|||||
|
35 |
||||
|
10 |
||||
|
155 |
||||
|
15 |
||||
|
20 |
||||
|
235 |
||||
Total Capitalized Exploration |
9 |
||||
Total Sustaining |
105 |
||||
Total Capital Budget |
349 |
||||
Principal assumptions used in the preparation of guidance for 2016 include:
Gold price: |
Lead price: |
|||
Silver price: $16/oz |
Zinc price: $2,000/t |
|||
CAD vs
Kisladag
In 2015 the original production budget for Kisladag was estimated between 230,000-245,000 ounces of gold at cash costs of
In 2016, Kisladag is expected to place 15 million tonnes of ore on the leach pad at a grade of 0.80 grams per tonne gold. Due to the current gold prices, the Company has planned to reduce the ROM material placed on the leach pad, which is expected to result in 13 million tonnes of crushed ore and 2 million tonnes of ROM for the year. The projected cash costs of
Looking ahead at 2017, the Company expects the average grade placed on the Kisladag leach pad to increase to approximately 0.90 grams per tonne gold, and production to increase to over 250,000 ounces.
Efemcukuru
During 2015 Efemcukuru met the original production guidance of 90,000-100,000 ounces of gold with cash costs between
The budget for 2016 includes mining and processing over 450,000 tonnes of ore at a grade of 7.5 grams per tonne gold. Operating costs are expected to be in-line with the 2015 forecast at
Production for 2017 is expected to continue at these levels.
During 2016, Stratoni is expected to process 220,000 tonnes of ore at grades of 6.2% lead, 10.0% zinc and 163 grams per tonne silver. Sustaining capital costs for the year are expected to total
Skouries
As of
Olympias
Phase I tailings re-processing will no longer be treated after the first quarter of 2016. The environmental reclamation will continue throughout 2016 with any remaining tailings being placed in the Kokkinolakas tailing storage facility. Phase II plant refurbishment is planned to commence as soon as the Phase I plant is decommissioned. Approximately
Jinfeng
During 2015, Jinfeng produced 149,700 ounces of gold at cash costs of
In 2016 Jinfeng is expected to process 930,000 tonnes of ore at a grade of 3.89 grams per tonne gold. The ore will be strictly sourced from the underground operations and a small amount of stockpile, as the open pit operations were successfully completed in
Major capital items include underground development to increase mine capacity for the processing of 1.2 million tonnes of ore by 2018 and the facilities required for the expanded underground work.
Tanjianshan
At Tanjianshan in 2015, the Company met all original targets with 97,600 ounces of gold produced at an average cash cost of
For 2016, the Company expects to process 1.1 million tonnes of ore at a grade of 2.39 grams per tonne. The drop in grade from 3.14 grams per tonne gold in 2015 is related to limited material being mined from the JLG pit with the remaining material being sourced from existing stockpiles. Sustaining capital spending is budgeted at
Planned 2017 production throughput and grade will vary depending on continued exploration success at Qinlongtan throughout 2016.
During 2015,
For 2016 the Company expects to process 850,000 tonnes of ore at a grade of 3.24 grams per tonne gold to produce 75,000-85,000 ounces at cash costs between
Production in 2017 is expected to increase as total tonnage increases to 950,000 tonnes at a similar grade.
Eastern Dragon
At Eastern Dragon, the Company plans to spend approximately
Certej
The Company's plans for Certej are progressing on schedule. The Company will spend approximately
Vila Nova
At Vila Nova, the iron ore mine remains on care and maintenance due to the depressed iron ore market price.
Tocantinzhino
Additional optimization studies are planned for 2016 at the Tocantinzhino project, which underwent a positive feasibility study optimization in 2015. The Company will spend
2016 Financial Outlook
The Company's balance sheet remains one of the strongest amongst its peers, with approximately
Depreciation, depletion and amortization expense is expected to be approximately
2015 Fourth Quarter and Year End Financials Announcement
The 2015 Fourth Quarter and Year End Financials will be released after the market closes on
Conference Call Details |
Replay (available until |
||||||
Date: |
|
|
416 849 0833 |
||||
Time: |
|
Toll Free: |
855 859 2056 |
||||
Dial in: |
647 427 7450 |
Pass code: |
3377 5022 |
||||
Toll free: |
888 231 8191 |
||||||
Certain of the statements made herein may contain forward-looking statements or information within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or "believes" or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. Forward-looking statements or information herein include, but are not limited to the Company's Preliminary 2015 Results and 2016 Guidance.
Forward-looking statements and forward-looking information by their nature are based on assumptions and involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. We have made certain assumptions about the forward-looking statements and information, including assumptions about the political and economic environment that we operate in, the future price of commodities and anticipated costs and expenses. Even though our management believes that the assumptions made and the expectations represented by such statements or information are reasonable, there can be no assurance that the forward-looking statement or information will prove to be accurate. Furthermore, should one or more of the risks, uncertainties or other factors materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements or information. These risks, uncertainties and other factors include, among others, the following: political and economic environment, gold price volatility; discrepancies between actual and estimated production, mineral reserves and resources and metallurgical recoveries; mining operational and development risk; litigation risks; regulatory environment and restrictions, including environmental regulatory restrictions and liability; risks of sovereign investment; currency fluctuations; speculative nature of gold exploration; global economic climate; dilution; share price volatility; competition; loss of key employees; additional funding requirements; and defective title to mineral claims or property, as well as those factors discussed in the sections entitled "Forward-Looking Statements" and "Risk Factors" in the Company's Annual Information Form & Form 40-F dated
There can be no assurance that forward-looking statements or information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, you should not place undue reliance on the forward-looking statements or information contained herein. Except as required by law, we do not expect to update forward-looking statements and information continually as conditions change and you are referred to the full discussion of the Company's business contained in the Company's reports filed with the securities regulatory authorities in
About
Eldorado is a leading low cost gold producer with mining, development and exploration operations in
SOURCE