Eldorado Achieves Record Annual Production with All-In-Sustaining-Costs of $780/oz
TSX: ELD NYSE: EGO
Highlights
- Record gold production of 789,224 ounces (including Olympias production from tailings retreatment), in-line with original 2014 guidance of 730,000-800,000 ounces of gold.
- 2014 all-in sustaining cash costs averaged
$780 per ounce; cash operating costs averaged$500 per ounce.
- Significant advancement of construction at Skouries: completion of the mill foundations; installation of the SAG and ball mills; and construction of the tailings dam began during the fourth quarter.
- Closed the year with total liquidity of approximately
$875 million , including$500 million in cash, cash equivalents and term deposits, and$375 million in lines of credit.
- 2015 forecast gold production estimated to be 640,000-700,000ounces of gold at an average cash cost ranging between
$570-615 per ounce, and an all-in sustaining cash cost between$960-995 per ounce.
- An eligible dividend of CDN
$0.01 per common share will be paid onFebruary 16, 2015 .
"The Company delivered another solid year with all of our mines either meeting or exceeding the original 2014 guidance. Costs were kept within the lower quartile of the industry average, crucial when we are faced with a period when metal prices remain depressed across the board." said Paul Wright, Chief Executive Officer of Eldorado.
"We are driving our development projects forward and I would like to highlight the significant progress made during 2014 at Skouries. The mill foundations and the installation of the SAG and regrind mills were completed and installation of the ball mill will be completed in the second quarter. We look forward to advancing Skouries throughout 2015, along with commencing construction on the
Eldorado's year-end financial statements are scheduled to be released on
| 2014 Operating Results | |||||
| 2014 Q4 | 2014 | ||||
| Realized Gold Price ($/oz) | 1,199 | 1,266 | |||
| Gold Sold (oz) | 203,952 | 774,522 | |||
| Gold Produced (oz) 1 | 199,572 | 789,224 | |||
| Cash Cost ($/oz) | 505 | 500 | |||
| Kisladag | |||||
| Gold Sold (oz) | 89,410 | 311,451 | |||
| Gold Produced (oz) | 89,148 | 311,233 | |||
| Tonnes to Pad | 4,687,620 | 15,501,790 | |||
| Grade (g/t) | 0.96 | 1.01 | |||
| Cash cost ($/oz) | 464 | 443 | |||
| Jinfeng | |||||
| Gold Sold (oz) | 42,177 | 168,432 | |||
| Gold Produced (oz) | 42,219 | 168,503 | |||
| Tonnes Milled | 380,818 | 1,470,824 | |||
| Grade (g/t) | 3.92 | 3.99 | |||
| Cash cost ($/oz) | 531 | 575 | |||
| Tanjianshan | |||||
| Gold Sold (oz) | 28,058 | 107,614 | |||
| Gold Produced (oz) | 28,058 | 107,614 | |||
| Tonnes Milled | 221,741 | 1,045,440 | |||
| Grade (g/t) | 4.73 | 3.70 | |||
| Cash cost ($/oz) | 359 | 389 | |||
| Gold Sold (oz) | 19,705 | 85,308 | |||
| Gold Produced (oz) | 19,705 | 85,308 | |||
| Tonnes Milled | 217,859 | 850,782 | |||
| Grade (g/t) | 3.45 | 3.47 | |||
| Cash cost ($/oz) | 638 | 617 | |||
| Efemcukuru | |||||
| Gold Sold (oz) | 24,602 | 101,717 | |||
| Gold Produced (oz) | 19,988 | 98,829 | |||
| Tonnes Milled | 112,703 | 436,852 | |||
| Grade (g/t) | 7.77 | 8.34 | |||
| Cash cost ($/oz) | 674 | 573 | |||
| Olympias | |||||
| Gold Sold (oz) | - | - | |||
| Gold Produced (oz) 2 | 454 | 17,737 | |||
| Tonnes Milled | 175,244 | 625,345 | |||
| Grade (g/t) | 2.27 | 2.70 | |||
| Cash cost ($/oz) | n/a | n/a | |||
| 1 Includes Olympias tailings retreatment 2 All tailings retreatment |
|||||
| 2014 Operating Results (Continued) | |||
| 2014 Q4 | |||
(Lead/Zinc Concentrate) |
|||
| Tonnes Sold (oz) | 12,129 | ||
| Tonnes Produced (oz) | 50,634 | ||
| Cash cost ($/t) | 821 | ||
(Iron Ore) |
|||
| Tonnes Sold (oz) | 84,652 | ||
| Tonnes Produced (oz) | 175,763 | ||
| Cash cost ($/t) | 34 | ||
Throughout this press release we use cash operating cost per ounce, all-in sustaining cost per ounce, gross profit from gold mining operations, adjusted net earnings and cash flow from operating activities before changes in non-cash working capital as additional measures of Company performance. These are non IFRS measures. Please see page 11 of the Third Quarter MD&A for an explanation and discussion of these non IFRS measures. All dollar amounts are stated in US $ unless stated otherwise.
2015 Guidance
| Mine | 2015 Production (Au oz) |
Cash Costs ($/oz) |
Sustaining Capital Expenditure ($ M) |
| Kisladag | 230,000-245,000 | 600-650 | 70 |
| Efemcukuru | 90,000-100,000 | 550-600 | 25 |
| Jinfeng | 135,000-145,000 | 660-700 | 30 |
| Tanjianshan | 90,000-100,000 | 475-500 | 20 |
|
|
70,000-75,000 | 650-690 | 20 |
| Olympias | 20,000-25,000 1 | N/A | 0 |
| Eastern Dragon | 5,000-10,000 | 100-125 | 0 |
| Total | 640,000-700,000 2 | 570-615 | 165 |
1All tailings retreatment
2 Includes Olympias tailings retreatment
Principal assumptions used in the preparation of guidance for 2015 include:
| Gold Price | /oz |
CAD vs |
||
| Silver Price | /oz |
RMB vs |
||
| Lead Price | /tonne |
REAL vs |
||
| Zinc Price | /tonne |
USD vs |
||
| TRL vs |
In 2015, Kisladag is expected to place 17.5 million tonnes of ore on the leach pad at a grade of 0.70 grams per tonne gold, including 4.6 million tonnes of run of mine (ROM) ore. The increase in costs are mainly grade related due to ore being mined from a lower grade portion of a new pit phase. Sustaining capital expenditures for the year are estimated to be
Efemcukuru is expected to mine and process 450,000 tonnes of ore at a grade of 7.69 grams per tonne gold. Sustaining capital expenditures for 2015 are estimated to be approximately
During 2015,
Development work at Skouries is planned to continue through 2015. Approximately
Olympias Phase I tailings re-processing will continue during 2015 and an additional 20,000 ounces of gold are expected to be recovered. Capital spending in 2015 is planned for
At
Jinfeng will process 1.3 million tonnes of ore at a grade of 3.95 grams per tonne gold. The ore will be primarily sourced from the underground operations, with the open pit operations being completed early in 2015. Sustaining capital costs for 2015 are estimated at
At Tanjianshan, the Companyexpects to process 1.1 million tonnes of ore at a grade of 3.36 grams per tonne in 2015. Sustaining capital spending is budgeted at
Finally, at Eastern Dragon, the Company plans to spend approximately
The Company's plans for Certej are progressing on schedule. The Feasibility study that commenced during the third quarter 2014 is scheduled for completion in the second quarter of this year. For 2015, the Company expects to spend approximately
At
The Tocantinzhino project, which had been undergoing a feasibility study optimization throughout 2014, has also been placed on hold. The Company will spend
2015 Financial Outlook
The Company's balance sheet remains one of the strongest amongst its peers, with approximately
Exploration expenditures in 2015 are budgeted at
Depreciation, depletion and amortization expense is expected to be approximately
Dividend
The Company is declaring that it will pay an eligible dividend of CDN
About
Eldorado is a leading low cost gold producer with mining, development and exploration operations in
Certain of the statements made herein may contain forward-looking statements or information within the meaning of
Forward-looking statements and forward-looking information by their nature are based on assumptions and involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. We have made certain assumptions about the forward-looking statements and information, including assumptions about the legal restrictions regarding the payment of dividends by the Company; assumptions about the price of gold; anticipated costs and expenditures; estimated production, mineral reserves and metallurgical recoveries; financial position, reserves and resources and gold production;and the ability to achieve our goals. Although our management believes that the assumptions made and the expectations represented by such statements or information are reasonable, there can be no assurance that the forward-looking statements or information will prove to be accurate. Furthermore, should one or more of the risks, uncertainties or other factors materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements or information. These risks, uncertainties and other factors include, among others, the following: gold price volatility; risks of not meeting production and cost targets; discrepancies between actual and estimated production, mineral reserves and resources and metallurgical recoveries; mining operational and development risk; litigation risks; regulatory restrictions, including environmental regulatory restrictions and liability; risks of sovereign investment and operating in foreign countries; currency fluctuations; speculative nature of gold exploration; global economic climate; dilution; share price volatility; competition; loss of key employees; additional funding requirements; and defective title to mineral claims or property, as well as those factors discussed in the sections entitled "Forward-Looking Statements" and "Risk Factors" in the Company's Annual Information Form & Form 40-F dated
There can be no assurance that forward-looking statements or information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, you should not place undue reliance on the forward-looking statements or information contained herein. Except as required by law, we do not expect to update forward-looking statements and information continually as conditions change and you are referred to the full discussion of the Company's business contained in the Company's reports filed with the securities regulatory authorities in
SOURCE