Kişladağ mine

Show printable version of 'Summary' in a New WindowEmail 'Summary' to a friend
 Summary
 
LOCATION Uşak, Turkey
PROPERTY SIZE 157 km²
RESERVES (in ounces Au)
Proven + Probable 6,816,000 @ 0.97 g/t
RESOURCES (in ounces Au)
Measured + Indicated
Inferred
10,273,000 @ 0.78 g/t
2,950,000 @ 0.50 g/t
PRODUCTION (in ounces Au)
2006
2007
2008
2009
2010 Forecast
2011 Forecast
70,895
135,306
190,334
237,210
255,000 to 265,000
270,000 to 280,000
CASH OPERATING COST (per ounce Au)
2006
2007
2008
2009
2010 Forecast
2011 Forecast
$206
$189
$254
$280
$300-$310
$300-$320
OWNERSHIP 100% (through Eldorado’s wholly owned Turkish subsidiary Tüprag Metal Madencilik Sanayi ve Ticaret - "Tüprag")
PROJECT STATUS AND HISTORY
  • Operating mine.
  • Implementing expansion project during 2010
  • Commercial production began in Q3 2006
  • First gold poured in Q2 2006
  • Construction Permit received in Q3 2004
  • Environmental Positive Certificate received in Q2 2003
  • Feasibility Study completed in Q1 2003

Description


The Kişladağ gold mine is the largest gold mine in Turkey. We advanced Kişladağ from an exploration discovery through development to construction and production. Kişladağ is a low grade, bulk tonnage open pit operation using heap leaching for gold recovery. The mine operates at a total ore throughput of 10 million tonnes per year. We are implementing the expansion project that will increase production to 12 million tonnes per year commencing in 2011. Capital expenditure for the project is budgeted at $40 million.

In Q1 2010, we produced 82,240 ounces of gold at a cash operating cost of $305 per ounce, a quarterly record for gold production at Kişladağ. The increased production resulted from improvements to the processing circuit with the introduction of intermediate leaching and larger carbon columns.

Kişladağ Mine Site


Resources and Reserves


As of December 31, 2009

GOLD

Mineral Reserves     Mineral Resources
Project Tonnes
(x1000)
Grade
(Au g/t)
In-situ
Gold ounces
(x1000)
    Tonnes
(x1000)
Grade
(Au g/t)
In-situ
Gold ounces
(x1000)
Kisladag                
Proven 68,230 1.05 2,312   Measured 82,904 0.93 2,490
Probable 149,240 0.94 4,504   Indicated 329,345 0.74 7,783
Proven+Probable 217,470 0.97 6,816   M+I 412,249 0.78 10,273
          Inferred 182,083 0.50 2,950



Files


Kişladağ Gold Mine Technical Report (PDF)
Kişladağ Project Feasibility Study Cost Update Executive Summary (PDF)
Kişladağ Project Feasibility Study (PDF)



Last update: May 20, 2010.