| LOCATION |
Uşak, Turkey |
| PROPERTY SIZE |
157 km² |
| RESERVES (in ounces Au) |
| Proven + Probable |
6,816,000 @ 0.97 g/t |
| RESOURCES (in ounces Au) |
Measured + Indicated Inferred |
10,273,000 @ 0.78 g/t 2,950,000 @ 0.50 g/t |
| PRODUCTION (in ounces Au) |
2006 2007 2008 2009 2010 Forecast 2011 Forecast |
70,895 135,306 190,334 237,210 255,000 to 265,000 270,000 to 280,000 |
| CASH OPERATING COST (per ounce Au) |
2006 2007 2008 2009 2010 Forecast 2011 Forecast |
$206 $189 $254 $280 $300-$310 $300-$320 |
| OWNERSHIP |
100% (through Eldorado’s wholly owned Turkish subsidiary Tüprag Metal Madencilik Sanayi ve Ticaret - "Tüprag") |
PROJECT STATUS AND HISTORY |
- Operating mine.
- Implementing expansion project during 2010
- Commercial production began in Q3 2006
- First gold poured in Q2 2006
- Construction Permit received in Q3 2004
- Environmental Positive Certificate received in Q2 2003
- Feasibility Study completed in Q1 2003
|
Description
The Kişladağ gold mine is the largest gold mine in Turkey. We advanced Kişladağ from an exploration discovery through development to construction and production. Kişladağ is a low grade, bulk tonnage open pit operation using heap leaching for gold recovery. The mine operates at a total ore throughput of 10 million tonnes per year. We are implementing the expansion project that will increase production to 12 million tonnes per year commencing in 2011. Capital expenditure for the project is budgeted at $40 million.
In Q1 2010, we produced 82,240 ounces of gold at a cash operating cost of $305 per ounce, a quarterly record for gold production at Kişladağ. The increased production resulted from improvements to the processing circuit with the introduction of intermediate leaching and larger carbon columns.
Kişladağ Mine Site
Resources and Reserves
As of December 31, 2009
GOLD |
Mineral Reserves |
|
|
Mineral Resources |
| Project |
Tonnes (x1000) |
Grade (Au g/t) |
In-situ Gold ounces (x1000) |
|
|
Tonnes (x1000) |
Grade (Au g/t) |
In-situ Gold ounces (x1000) |
| Kisladag |
|
|
|
|
|
|
|
|
| Proven |
68,230 |
1.05 |
2,312 |
|
Measured |
82,904 |
0.93 |
2,490 |
| Probable |
149,240 |
0.94 |
4,504 |
|
Indicated |
329,345 |
0.74 |
7,783 |
| Proven+Probable |
217,470 |
0.97 |
6,816 |
|
M+I |
412,249 |
0.78 |
10,273 |
| |
|
|
|
|
Inferred |
182,083 |
0.50 |
2,950 |
Files
Kişladağ Gold Mine Technical Report (PDF)
Kişladağ Project Feasibility Study Cost Update Executive Summary (PDF)
Kişladağ Project Feasibility Study (PDF)
Last update: May 20, 2010.
|