Your browser does not support script

Operating Mines

Fact Sheet

Electronic Investor Package

Presentation

Conference Call

Photo Gallery

Production Highlights

Search This Site


Kişladağ mine

Show printable version of 'Kisladag mine' item in a New WindowEmail 'Kisladag mine' item to a friend
 Summary
 
LOCATION Uşak, Turkey
PROPERTY SIZE 157 km²
RESERVES (in ounces Au; at December 31, 2010)
Proven + Probable 10,231,000 @ 0.74 g/t
RESOURCES (in ounces Au; at December 31, 2010)
Measured + Indicated
Inferred
12,189,000 @ 0.68 g/t
4,384,000 @ 0.43 g/t
PRODUCTION (in ounces Au)
2006
2007
2008
2009
2010
2011
2012 Forecast
70,895
135,306
190,334
237,210
274,592
284,648
285,000-295,000
CASH OPERATING COST (per ounce Au)
2006
2007
2008
2009
2010
2011
2012 Forecast
$206
$189
$254
$280
$329
$374
$385-395
OWNERSHIP 100% (through Eldorado’s wholly owned Turkish subsidiary Tüprag Metal Madencilik Sanayi ve Ticaret SA - "Tüprag")
PROJECT STATUS AND HISTORY
  • Operating mine
  • Announced study for Phase IV expansion to 25 million tonnes per year. Supplementary Environmental Impact Assessment to be submitted in Q2 2012; approval anticipated Q3 2012. Project completion estimated for Q3 2014
  • Received permit to increase throughput to 12.5 million tonnes of ore per year in 2011
  • Began commercial production in Q3 2006
  • Poured first gold in Q2 2006
  • Received construction permit in Q3 2004
  • Received Environmental Positive Certificate in Q2 2003
  • Completed Feasibility Study in Q1 2003

Description


The Kişladağ gold mine is the largest gold mine in Turkey. We advanced Kişladağ from an exploration discovery through development to construction and production. Kişladağ is a low grade, bulk tonnage open pit operation using heap leaching for gold recovery.

In 2011 we placed 12.4 million tonnes of ore on the leach pad. The increased ore production (from 10 million tonnes in 2010) was the result of the expansion project undertaken in 2010.

Capital spending in 2012 is estimated at $175 million. Most of this is for the commencement of engineering works on the expansion project to take Kişladağ up to 25 Mtpa of crushed material, plus 8 Mtpa of run-of-mine material. The total cost for this project is $354 million and commissioning is expected during 2014.

In August 2011 we announced the results of the Phase IV expansion study which involves processing an additional 12.5 million tonnes per year -- for a total of 25 million tonnes. We intend to submit the supplementary Environmental Impact Assessment report in Q2 2012 and anticipate receiving approval in Q3 2012. We estimate that the Phase IV expansion will be completed by Q3 2014 - resulting in an average expanded production rate of approx. 475,000 ounces of gold per year from Kisladag.





Kişladağ Open Pit


Resources and Reserves



As of December 31, 2010



GOLD

Mineral Reserves

     

 

Mineral Resources

 

tonnes
(x1000)

grade
(g/t)

in-situ oz
(x1000)

 

 

tonnes
(x1000)

grade
(g/t)

in-situ
oz
(x1000)

Kisladag

 

 

 

 

 

 

 

 

Proven

122,703

0.95

3,733

 

Measured

132,800

0.90

3,855

Probable

306,631

0.66

6,498

 

Indicated

426,355

0.61

8,334

Proven & probable

429,334

0.74

10,231

 

M+I

559,155

0.68

12,189

 

 

 

 

 

Inferred

320,868

0.43

4,384


Subsequent Events:

Kisladag Resource and Reserve Update - Kisladag Resource and Reserve Update Reserves Continue to Grow


Files


Kişladağ Gold Mine Technical Report (PDF)
Kişladağ Project Feasibility Study Cost Update Executive Summary (PDF)
Kişladağ Project Feasibility Study (PDF)



Last update: January 25, 2012.
 
 Location
 Location Map

The Kişladağ mine is located 180 kilometres east of Izmir and 350 kilometres southwest of Ankara, in Uşak Province. The city of Uşak with a population of 170,000 is the closest large population centre, located 35 kilometres to the northeast. Access to the site is via all-weather paved roads serving several small villages in the immediate area.

Kişladağ sits on the western edge of the Anatolian Plateau, in gentle rolling topography, at an elevation of approximately 1,000 metres. The climate is arid with hot summers and cold winters. Economic activity in the area consists of a mixture of subsistence farming and grazing.

Last update: April 7, 2010.
 
 Geology & Mineralization
 Kişladağ lies within one of several mid- to late-Tertiary volcanic complexes in western Turkey, related to subduction along the Hellenic Trench southwest of Turkey. In the Kişladağ region, the volcanic complexes erupted onto a basement of schist at the northeast margin of the Menderes Massif.

Porphyry-style gold mineralization is hosted by a number of latitic intrusive bodies. The Gökgöz Tepe alteration zone, which encloses the Kişladağ deposit, covers approximately 12 square kilometers. Intensely-altered coarsely porphyritic latite is host to the bulk of the gold mineralization. The ore body forms an annular zone around a later weakly mineralized stock of similar composition. Gold is associated with multiple phases of tourmaline-pyrite, pyrite, and quartz-pyrite veins and breccias, and is accompanied by small amounts of base metals, principally zinc and molybdenum. Oxidation in the deposit is shallow over the barren intrusion but extends to depths of 40 to 50 meters to the west and east.





Last update: April 7, 2010.
 
 Mining & Processing
 In 2012, Kişladağ plans to place 12.5 million tonnes of ore on the leach pad at a grade of 1.08 g/t Au, with a strip ratio of 1.3:1. The 12.5 million tonnes is the design capacity for the new equipment commissioned in 2011. In 2010, we increased ore production to 10 million tonnes by adding capacity to the crushing and conveying circuits.

Initial mining at Kişladağ was carried out by a local contractor using conventional earth-moving equipment. An owner-operated fleet of 150 tonne haul trucks and equivalent loading equipment was brought into operation in Q3 2008.

A three-stage crushing system using a gyratory crusher and four cone crushers reduces the run-of-mine ore to 80% passing 6.3 mm in size for leaching. Conveyors are used to transfer and distribute the material onto the leach pad in 10 meter lifts for leaching. A conventional carbon adsorption facility (ADR plant) is used to recover the gold from process solutions to a final gold dore product.

Kişladağ cash costs have been impacted by increases in price of fuel, reagents, consumables as well as a slight decline in the ore grade and increase in the waste stripping. The overall effects have however been partially offset by process efficiency improvements.



Last update: January 25, 2012.
 
 Kişladağ Exploration
 To take full advantage of the Kişladağ mine's processing facilities, we continue to look for new opportunities in the area surrounding the mine.

Exploration at Kişladağ in 2012 will be a continuation of the 2011 geophysical surveying for deep target generation, with diamond drill testing (10,000 metres) of identified targets.

Drilling to October 2011 included 12 diamond drillholes testing fault-controlled hydrothermal conduits emanating southward from the deposit area, and investigating areas reserved for infrastructure expansion. No significant mineralized intersections were obtained.

Following our 2009 and 2010 resource drilling programs, the 2011 exploration program shifted to new target generation peripheral to the main porphyry system, focusing on possible satellite deposits concealed beneath volcanic cover. We conducted soil sampling and a 3-dimensional IP survey covering approximately 40 km2 surrounding the deposit to identify new targets.

Kişladağ Section Showing Mineralized Zones, Southern Area (Click to enlarge)



Kişladağ Plan (Click to enlarge)




Last update: January 25, 2012.
 
 Related News
 
January 09, 2012  2011 Operating Results / 2012 Operating Guidance Dividend Payment Increases 50%
October 12, 2011  Operational Update. Record Quarterly Production - 179,195 oz @ $397/oz
October 06, 2011  Eldorado Gold Announces Exploration Programs Update
August 19, 2011  Eldorado Gold Announces Results of the Kisladag Expansion Study Higher Production Continued Low Costs
July 28, 2011  2011 Second Quarter Financial and Operating Results
June 13, 2011  Eldorado Gold Achieves Two Key Permitting Milestones in Turkey
 
 
 
 Kisladag Gallery
 

Photo Gallery

Click on the picture to enlarge
Kisladag Gold Mine - Aerial Views
(August 2010)
Kisladag Gold Mine - Aerial Views
(August 2010)
Kisladag Gold Mine - Aerial Views
(August 2010)
Kisladag Gold Mine - Aerial Views
(August 2010)
May 2010 - Open pit
May 2010 - Open pit
May 2010 - Mining operations
May 2010 - Coarse ore stock pile
May 2010 - Ore screening area
May 2010 - ADR plant
December 2008 - Kisladag stacking system
December 2008 - Kisladag at night
December 2008 - Kisladag mine panoramic
December 2008 - Kisladag heap leach pad
December 2008 - Kisladag stacking system
October 2008 - Kisladag mining fleet
December 2008 - Kisladag open pit
March 6, 2008 Kisladag Up & Running Back Hoe Loading 150 Ton Truck
March 6, 2008 Truck Dumping into Primary Crusher
Kisladag Mine Crushing and Screening Plant August 2006
Kisladag Mine with Second Line of Crushers March, 2007
Kisladag Mine
Kisladag Leach Pad Stacking System
Kisladag Gold Mine Official Opening Ceremonies
Dignitaries and Company Officials at the controls to officially open the mine with a blast
Kisladag Gold Bar
Watching Gold Pour
First Gold from Kisladag Mine
Mehmet Yilmaz, Public Relations Manager with first gold from Kisladag Mine
Open Pit Pre-production Mining
Open Pit Contract Mining
Crushing Screening Plant
Fine Ore Loadout
Overland Conveyor Feed End
Overland Tripper Conveyor
Gold Recovery Plant
Leach Pad under Irrigation
Solution Ponds and Gold Recovery Plant
Kisladag Mine
Leach Pad
Industrial Resources
ADR Plant
Pit
Leach Pad
Industrial Area Crushing Screening Plants
ADR Plant
Open Pit
ADR Plant
Leach Pad
Crushing Screening Plant Site
Administration Offices
Open Pit
Administration Office
Plant Site
ADR Plant Site
Over Liner
Leach Pad
Leach Pad Construction
Crusher Foundation
Leach Pad Construction
Kisladag ADR Plant Foundation
Turkey Kisladag Exploration - Cross Section
Successful Gold Pour
--
:Show picture in New Window:
--